Weekly Construction Update

This update is going to be terrible. lol My husband did not take good notes during the telephone call and instead focused on addressing some issues I wanted him to inquire about.

Here it is...the HVAC installation will be this week...that's all. I have no clue what will be going on next week.

Issues addressed during phone call

  • My husband asked about the fungus growing in the master shower and he was told this...
    • It is not mold or fungus. The tile guys made a mess when they were putting in the tile and it just needs to be cleaned up. Ummmm....no. I beg to differ and sent a text message with pictures to the sales manager stating that there was clearly something growing and that they drywall needed to be cut out.
  • Missing pendant light connection over the island
    • The construction manager believes they forgot to cut the hole in the drywall. It will be fixed.
  • Discoloration in corner of plant ledge (difficult to photograph)
    • He had noticed it and will have the guys take a look at it
Believe me, I will be looking at everything very closely tommorow.